# Liquidated Damages Clause

Source: https://contracko.com/es/biblioteca-de-clausulas/clausula-penal

# Liquidated Damages Clause

Fixes in advance the sum payable on a specified breach, sparing the parties from proving actual loss.

## Qué es

A liquidated damages (or penalty) clause sets a predetermined amount payable if a defined breach occurs, commonly late delivery or breach of confidentiality. In Dutch law this is the boetebeding, which can serve as compensation, as a penalty, or both.

## Por qué importa

It gives certainty and a strong incentive to perform without the cost of proving loss. But a court may mitigate an excessive penalty under BW 6:94, so the amount should be a genuine pre-estimate, not punitive.

## Cómo aplicarla

- Tie the sum to a realistic estimate of likely loss to reduce mitigation risk.
- State whether the penalty replaces or supplements actual damages.
- Specify the exact breach that triggers the penalty and any cap or per-day rate.
- Clarify whether a notice of default is required before the penalty is due.

## Consejos de negociación

- • The paying party should cap the aggregate penalty and demand a default-notice trigger.
- • The receiving party should exclude the court's power to mitigate where lawfully possible.

## Errores frecuentes

- • Setting a punitive amount unconnected to loss, risking mitigation under BW 6:94.
- • Failing to state whether the penalty excludes a separate damages claim.

### Cómo ayuda Contracko

Contracko's AI review flags liquidated-damages clauses across your contracts and highlights missing caps, absent notice-of-default requirements and amounts that appear disproportionate to contract value. Penalty trigger dates, such as agreed delivery deadlines, are tracked as contract milestones with reminders, so your operations team can act before a breach accumulates an avoidable penalty.

## Referencias legales

- [BW 6:91 Penalty clause (boetebeding) Derecho neerlandés](https://wetten.overheid.nl/BWBR0005289)
- [BW 6:94 Judicial mitigation of a penalty Derecho neerlandés](https://wetten.overheid.nl/BWBR0005289)

Salvo indicación en contrario, las referencias remiten al derecho neerlandés (Burgerlijk Wetboek, el Código Civil neerlandés); los instrumentos de la UE como el RGPD se aplican en toda la UE. Se trata de información general, no de asesoramiento legal. Otras jurisdicciones tratan estos conceptos de forma distinta. Verifique el texto vigente y su situación con un abogado cualificado.

## Relevante para

[Construcción](https://contracko.com/es/sectores/industria-construccion)[Logística y distribución](https://contracko.com/es/sectores/logistica)[Industria manufacturera](https://contracko.com/es/sectores/fabricacion)[Ingeniería y arquitectura](https://contracko.com/es/sectores/ingenieria)[Gestión de eventos](https://contracko.com/es/sectores/gestion-eventos)

## Cláusulas relacionadas

- [Payment Terms Clause](https://contracko.com/es/biblioteca-de-clausulas/condiciones-de-pago)
- [Termination for Cause Clause](https://contracko.com/es/biblioteca-de-clausulas/resolucion-por-incumplimiento)
- [Confidentiality Clause](https://contracko.com/es/biblioteca-de-clausulas/clausula-de-confidencialidad)

## Términos relacionados

- [Liquidated damages](https://contracko.com/es/glosario/clausula-penal)
- [Breach of contract](https://contracko.com/es/glosario/incumplimiento-de-contrato)
- [Liability](https://contracko.com/es/glosario/responsabilidad)

### No vuelva a perder un plazo de contrato

- La IA encuentra las fechas de renovación y preaviso
- Los riesgos y obligaciones afloran automáticamente
- Los recordatorios le ayudan a actuar antes de que las fechas se escapen

Suelte un contrato para empezar

PDF, DOCX, PNG o JPG

[Empezar prueba de 7 días](https://app.contracko.com/register?appLanguage=es&utm_source=clause_library_sidebar&utm_medium=lead_magnet&utm_campaign=clause_library_sidebar_contract_upload&content_slug=liquidated-damages&content_title=Liquidated+Damages+Clause&cta_placement=clause_library_sidebar_cta&source_tool=clause_library_sidebar_liquidated-damages)

Conforme con el RGPD. Cifrado. Nunca se usa para entrenar la IA.

## Preguntas frecuentes

Preguntas comunes sobre esta cláusula.

- **Q:** Can a Dutch court reduce a contractual penalty?
  **A:** Yes. Under BW 6:94 a court may mitigate a penalty if fairness manifestly requires it, even where the parties agreed the amount.

- **Q:** Can I also claim actual damages on top of a penalty?
  **A:** Only if the clause says so. By default the penalty replaces statutory damages, so state expressly whether both are recoverable.

- **Q:** Is a notice of default always required before a penalty is due?
  **A:** Not if a hard deadline has passed automatically; otherwise, Dutch law generally requires putting the debtor in default first. The clause should state this clearly to avoid uncertainty.

- **Q:** How should the penalty amount be set to reduce the risk of judicial mitigation?
  **A:** It should represent a genuine pre-estimate of the likely loss at the time of contracting, not a punitive sum. Documenting the rationale at the time of drafting strengthens enforceability.

- **Q:** Can a penalty clause accrue indefinitely?
  **A:** Only if there is no aggregate cap. Most well-drafted clauses set a maximum total amount or a per-day rate with a ceiling to limit exposure for both parties.

## No vuelva a perder nunca una cláusula de riesgo

Contracko revisa automáticamente cada contrato en busca de esta cláusula y de las obligaciones que genera.

[Iniciar la prueba gratuita de 7 días](https://app.contracko.com/register?appLanguage=es)

Reservar demo