# Liquidated damages

Source: https://contracko.com/fr/glossaire/clause-penale

# Liquidated damages

A pre-agreed sum payable on breach, set in advance instead of proving actual loss.

## Définition

Liquidated damages are a sum the parties agree in advance will be payable if a specified breach occurs, sparing the need to prove actual loss. In Dutch law this is the boetebeding (penalty clause), recognised in articles 6:91 to 6:94, where the agreed amount can replace or supplement statutory damages. A court may, under article 6:94, moderate a penalty that is manifestly excessive in the circumstances.

## Exemple

> A construction contract sets €2,500 per day of late completion as liquidated damages; the client need not prove its exact losses to claim them.

## Pourquoi c'est un risque pour l'entreprise

An uncapped liquidated-damages clause can transform a performance failure into a catastrophic financial liability. Suppliers who sign contracts without checking whether penalties are proportionate to the contract value may find themselves facing claims that dwarf their fee. Customers who set the figure too low may find it is insufficient to cover actual losses and have waived the right to claim the difference.

## Comment le gérer

- Cap liquidated damages as a percentage of contract value (e.g. 10-20%) so they remain commercially proportionate.
- State whether liquidated damages are the sole remedy for the specified breach or whether the injured party can also claim actual loss above that figure.
- Set the daily or weekly rate with reference to the genuine pre-estimate of harm; a rate that is purely punitive may be reduced by a Dutch court.
- Track trigger events centrally so you know when a penalty clock has started and can act before it accumulates unduly.

### Comment Contracko aide

Contracko extracts liquidated-damages clauses, their triggers, daily rates, and caps as searchable contract metadata. Obligation tracking can alert you when a milestone is at risk of being missed so you can take corrective action before a penalty clause is triggered.

## Références juridiques

- [BW 6:91 Dutch Civil Code: penalty clause Droit néerlandais](https://wetten.overheid.nl/BWBR0005289)
- [BW 6:94 Dutch Civil Code: judicial moderation of penalty Droit néerlandais](https://wetten.overheid.nl/BWBR0005289)

Sauf mention contraire, les références renvoient au droit néerlandais (Burgerlijk Wetboek, le Code civil néerlandais) ; les instruments de l'UE tels que le RGPD s'appliquent dans toute l'UE. Il s'agit d'informations générales, pas de conseils juridiques. D'autres juridictions traitent ces concepts différemment. Vérifiez le texte en vigueur et votre situation avec un avocat qualifié.

## Pertinent pour

[Construction](https://contracko.com/fr/secteurs/industrie-construction)[Logistique et distribution](https://contracko.com/fr/secteurs/logistique)[Industrie manufacturière](https://contracko.com/fr/secteurs/fabrication)[Ingénierie et architecture](https://contracko.com/fr/secteurs/ingenierie)

## Clauses associées

- [Liquidated Damages Clause](https://contracko.com/fr/bibliotheque-de-clauses/clause-penale)
- [Service Level Agreement (SLA)](https://contracko.com/fr/bibliotheque-de-clauses/accord-de-niveau-de-service)
- [Termination for Cause Clause](https://contracko.com/fr/bibliotheque-de-clauses/resiliation-pour-faute)

## Termes associés

- [Breach of contract](https://contracko.com/fr/glossaire/rupture-de-contrat)
- [Liability](https://contracko.com/fr/glossaire/responsabilite)
- [Service level agreement (SLA)](https://contracko.com/fr/glossaire/accord-de-niveau-de-service)

### Ne manquez plus jamais une échéance de contrat

- L'IA repère les dates de renouvellement et de préavis
- Les risques et obligations sont mis en évidence automatiquement
- Les rappels vous aident à agir avant que les dates ne filent

Déposez un contrat pour commencer

PDF, DOCX, PNG ou JPG

[Démarrer l'essai de 7 jours](https://app.contracko.com/register?appLanguage=fr&utm_source=glossary_sidebar&utm_medium=lead_magnet&utm_campaign=glossary_sidebar_contract_upload&content_slug=liquidated-damages&content_title=Liquidated+damages&cta_placement=glossary_sidebar_cta&source_tool=glossary_sidebar_liquidated-damages)

Conforme au RGPD. Chiffré. Jamais utilisé pour l'entraînement de l'IA.

## Foire aux questions

Questions courantes sur ce terme.

- **Q:** Can a Dutch court reduce an agreed penalty?
  **A:** Yes. Under article 6:94 BW a court may moderate a penalty if fairness manifestly requires it, for example where it is grossly disproportionate to the actual harm.

- **Q:** Do you need to prove actual loss to claim liquidated damages?
  **A:** No. The whole point of a liquidated-damages clause is to fix the recoverable sum in advance, making proof of loss unnecessary. This is particularly valuable for hard-to-quantify losses such as delayed project completion.

- **Q:** Is there a difference between liquidated damages and a penalty under Dutch law?
  **A:** Dutch law uses boetebeding for both concepts under BW 6:91-94. A court may moderate a grossly excessive penalty under 6:94, whether it was intended as compensation or punishment.

- **Q:** Can liquidated damages accumulate without a cap?
  **A:** Yes, unless the contract sets a cap. Without one, daily penalties can accumulate indefinitely until the breach is cured or the contract is terminated. Always negotiate a cap to limit total exposure.

- **Q:** Are liquidated damages common in SaaS contracts?
  **A:** Less so than in construction. SaaS contracts more commonly use service credits for SLA misses, which serve a similar function but are typically self-executing and much smaller in scale than construction-style liquidated damages.

## Voyez ces termes dans vos propres contrats

Téléversez un contrat et Contracko en extrait les termes, dates et obligations clés, puis vous rappelle chacun d'eux avant qu'il ne compte.

[Démarrer l'essai gratuit de 7 jours](https://app.contracko.com/register?appLanguage=fr)

Réserver une démo