What is a time and materials contract?
Say a regional logistics company hires a software agency to fix a failing warehouse scanner integration. Nobody knows how many hours it will take. So they sign a time and materials contract: $150 an hour for senior engineers, $110 for testers, test servers at cost, and a $60,000 cap. The agency must warn the buyer at 75 percent of the cap. If nobody watches that number, work stops halfway or an unplanned invoice arrives.
A time and materials (T&M) contract pays a provider for hours worked at agreed hourly rates, plus materials, usually at cost. This guide covers T&M contracts in the United States (US): federal contracts under the Federal Acquisition Regulation (FAR), and private business agreements governed by state contract law and their own terms. It is general information, not legal advice. The buyer usually carries the risk that the work runs long, and a ceiling or cap can limit that risk.
Time and materials contract: purpose and uses
A T&M contract usually buys effort rather than a defined result. It fits work whose size you cannot know at signing. Discovery and debugging, ongoing maintenance, emergency repairs, consulting, and repairs where conditions only show once work starts are common examples.
Federal rules state that condition directly. FAR 16.601 sets the basic condition for a US federal T&M contract. At the time of placing a federal contract, it must not be possible to estimate accurately the extent or duration of the work, or to anticipate costs with any reasonable degree of confidence [1]. Private buyers are not bound by that rule, but it is a useful test. When risk is minimal or can be predicted with an acceptable degree of certainty, FAR 16.103 says US federal buyers must use a firm fixed price [4].
Under a government-wide FAR overhaul, Acquisition.gov publishes rewritten model text for FAR Part 16 and lists many US federal agencies with posted Part 16 deviations [1]. That federal model text renumbers the T&M rules as 16.601-1 to 16.601-5 and keeps the ceiling and determination requirements described here [1]. Check which version, and which agency deviation, your federal contract or order cites.
Several names cover the same idea or a close variant:
| Term | What it means | Same as T&M? |
|---|---|---|
| Time and material, T&M | The same contract type, spelled differently | Yes |
| Capped or not-to-exceed (NTE) T&M | A T&M contract with a maximum price | Yes, with a cap |
| Labor-hour contract | Hourly rates only; the provider supplies no materials | A variant. For US federal contracts, FAR 16.602 calls it a variation of T&M [1] |
| Fixed-price contract | One agreed price for a defined result | No. The provider carries the overrun risk |
| Cost-reimbursement or cost-plus | Allowable costs plus a fee | No. It pays actual costs rather than fixed hourly rates |
Many service agreements combine models, for example a fixed-price build followed by T&M support. A service contract can use any of these pricing structures, so read the pricing schedule rather than the title.
Time and materials contract: parties
Most T&M contracts have two signatories. Federal contracts add named government roles.
- Buyer or client. The business or agency paying for the work. It typically approves timesheets and invoices, controls the budget, and decides whether the cap may rise, as the contract allows.
- Provider or contractor. The agency, consultancy, or contractor doing the work. It staffs the labor categories, keeps time records, and buys materials.
- Subcontractors. FAR 16.601 sets a rule for US federal contracts for other than commercial products or services that are awarded without adequate price competition. Those federal contracts must specify separate fixed hourly rates for each labor category performed by the contractor, each subcontractor, and each division, subsidiary, or affiliate under common control [1]. In private deals, the contract should say whether subcontractor hours are billed at the prime's rates.
- Contracting officer. In US federal work, this official signs the determination and findings (D&F) justifying the contract type. The federal contracting officer also approves vouchers, or names a representative who does, and raises the ceiling in writing [1] [2].
- Head of the contracting activity. This US federal official must approve the D&F before the base period starts when the base period plus any options exceeds three years [1].
On the buyer side, the people who approve hours are often not the people who signed. If you buy from many providers, the vendor contract guide covers supplier relationships more broadly.
Time and materials contract: key clauses
The pricing schedule is the heart of a T&M contract. These clauses decide what you actually pay. The FAR rules below apply only to US federal contracts. Private contracts set their own terms, and the federal rules are a useful model.
Labor categories and hourly rates. Each role gets a fixed hourly rate. Under FAR 16.601, US federal hourly rates include wages, overhead, general and administrative expenses, and profit [1]. Under the US federal payments clause, some labor goes unpaid. Where a federal contract specifies qualifications for a task, hours performed by employees who lack them are not paid, unless the contracting officer specifically authorizes it [2]. Private contracts often list required seniority or certifications for each rate.
Materials and other direct costs. In US federal contracts, materials include direct materials, subcontracts for supplies and incidental services with no labor category, other direct costs such as travel, and applicable indirect costs [1]. Except for the contractor's own commercial materials covered below, the US federal payments clause reimburses the allowable cost of materials on one of two conditions. The federal contractor has paid for them under the agreement or invoice, or it ordinarily pays under those terms within 30 days of its payment request [2]. Under that federal clause, the contractor's own commercial materials cost no more than its catalog or market price, adjusted for quantity and required modifications [2]. That federal clause also pays the prime contractor no profit or fee on materials, except as FAR 31.205-26(e) and (f) allow [2]. Those federal exceptions cover some transfers between the contractor's own affiliates under common control, which may be allowed at a price rather than at cost when that section's conditions are met [2]. Private contracts may bill materials at cost or with a stated markup. The contract should say which applies.
Ceiling price or not-to-exceed cap. In US federal T&M contracts, the contract or order must include a ceiling price that the contractor exceeds at its own risk [1]. Under the US federal payments clause, the government need not pay above the ceiling, and the contractor need not keep working past it, until the contracting officer raises it in writing [2]. When and to the extent the federal ceiling is raised, hours and material costs incurred above it before the increase are allowable to the same extent as if incurred after the increase [2]. In private contracts, what happens at the cap depends on the contract's wording.
Early warning. The US federal payments clause sets a notice point for the contractor. The federal contractor must notify the contracting officer when it has reason to believe the total will pass 85 percent of the ceiling. The federal test adds hourly-rate payments and material costs accruing in the next 30 days to all payments and costs accrued so far [2]. That federal notice gives a revised estimate of the total price, with supporting reasons and documentation. A federal contractor must give the same kind of notice if it has reason to believe the total price will be substantially greater or less than the ceiling [2]. In turn, the federal contracting officer will advise the contractor, with a revised estimate of effort, when the government has reason to believe the work will be substantially greater or less than the ceiling [2]. Private contracts often borrow this idea with their own threshold.
Overtime. Under the US federal payments clause, hourly rates do not change because work was done on overtime, unless the schedule says otherwise [2]. If a federal schedule has no overtime rates and the contracting officer approves overtime in advance, overtime rates are negotiated [2]. If a federal schedule has overtime rates, the premium portion is reimbursed only to the extent the contracting officer approved the overtime [2].
Invoices and records. US federal contractors may submit vouchers no more than once every two weeks, though a small business may receive more frequent payments [2]. Federal vouchers must be backed by evidence of actual payment. Federal vouchers also need daily job timekeeping records, records showing staff meet the labor category qualifications, or other substantiation the contracting officer approves [2]. Private contracts should name the invoice cycle, the timesheet format, and who approves hours.
Withholding and audit. Unless the schedule says otherwise, a US federal contracting officer may require a withhold of 5 percent of hourly-rate payments. The total federal withhold may not exceed $50,000 for the contract, and it is kept until the contractor delivers the final release of claims [2]. Before final payment, the US federal government may audit vouchers and reduce earlier payments found not properly payable [2].
Change control. Before increasing a US federal T&M ceiling, the contracting officer must analyze pricing and other relevant factors and document the decision [1]. When that federal change modifies the general scope, FAR 16.601(e) also points the contracting officer to separate procedures, depending on whether it is a contract or an order [1]. Private contracts need their own version: who can approve more hours, in what form, and what counts as a scope change.
Rate escalation, termination, and intellectual property clauses matter too. The clause glossary entry explains how these building blocks fit together.
Dates and lifecycle events
A T&M contract has fewer fixed dates than a subscription. The dates it has are tied to money.
- Before award. For US federal T&M contracts, the contracting officer signs the D&F before the base period and before any option period is executed [1]. For US federal commercial services, FAR 12.207 allows T&M only after competition or one of the other award procedures it lists [3]. That federal D&F has several required elements. Among them, the federal D&F must show that the extent, duration, or cost of the work could not be estimated with confidence at award. The federal D&F must also describe the market research and the actions planned to maximize fixed-price contracts on future acquisitions of the same requirement [3]. For US federal indefinite-delivery contracts, FAR 12.207(c) sets separate D&F rules for the basic contract and its T&M orders [3].
- Start and period of performance. The work window, plus any option periods.
- Invoice cycle. Weekly, biweekly, or monthly. US federal vouchers may be submitted no more than once every two weeks, though a small business may receive more frequent payments [2].
- Cap thresholds. The point at which the provider must warn the buyer. In US federal contracts, the trigger is the contractor's reason to believe the total will pass 85 percent of the ceiling. The federal test adds hourly-rate payments and material costs accruing in the next 30 days to all payments and costs accrued so far [2].
- Rate review dates. Many multi-year private contracts allow an annual rate increase on a set date or after notice.
- Option and renewal dates. The deadline to extend or let the contract end. The contract dates guide explains end dates, renewals, and notice periods.
- Completion and closeout. Under the US federal payments clause, the contractor submits a completion voucher no later than 120 days after completing the work, unless the contracting officer approves a longer period in writing [2]. Under that federal clause, a signed release of claims is a condition of final payment [2].
Map these events onto the contract lifecycle so each one has an owner, from award through closeout.
Risks and common mistakes
The main risk is built into the model. FAR 16.601 states that a US federal T&M contract gives the contractor no positive profit incentive for cost control or labor efficiency, so the federal government must monitor performance [1]. A private buyer faces the same incentive problem without a rule telling anyone to watch.
- No one tracks the cap. In US federal contracts, work above the ceiling is at the contractor's risk until the ceiling is raised [1] [2]. In private contracts, who bears an overrun depends on the contract's wording, so a missing cap can leave the buyer paying for every hour billed at the agreed rates.
- No change control. Extra requests arrive by email and become billable hours. Without a written approval step, nobody can say what the budget was for.
- Unqualified staff at senior rates. A junior engineer billed as a senior one inflates cost. In US federal contracts, where qualifications are specified for a task, hours worked by staff who lack them are not paid unless the contracting officer specifically authorizes it [2]. Private contracts need their own check.
- Markup on materials. If the contract says actual cost, a markup is an overcharge. If it allows a markup, it should state the percentage.
- Unapproved overtime. Overtime premiums should need advance approval in writing.
- Thin records. Without daily timesheets or similar records, invoices are hard to check and hard to challenge.
- T&M long after the scope is known. FAR 16.103 says US federal contracting officers should avoid protracted use of T&M contracts once experience provides a basis for firmer pricing [4]. Private buyers can apply the same rule at renewal.
These checks belong in your wider contract risk management routine. For a first pass on an incoming T&M agreement, the free artificial intelligence (AI) contract review tool flags key dates, obligations, payment terms, and unusual clauses [6].
Contract-management checklist
Use this list when you sign, run, and close a T&M contract.
Capture at signing:
- Parties, signatories, and the people allowed to approve hours
- Labor categories, qualifications, and hourly rates
- Materials terms: actual cost or markup, and any handling charges
- Ceiling or not-to-exceed amount, and the warning threshold
- Overtime rules and approval requirements
- Invoice cycle, timesheet format, and payment terms
- Change-control procedure and who signs changes
- Rate escalation terms, termination rights, and notice periods
- Audit rights and record retention terms
Diarise:
- Start date, end date, and option or renewal deadlines
- Warning threshold, set as a spend amount rather than a date
- Rate review and escalation dates
- Termination notice deadlines
- Closeout deadlines, such as the completion invoice and final release
Review on a cadence:
- Each invoice: hours against timesheets, rates against the schedule, materials against receipts
- Each month: spend to date against the cap and the forecast to completion
- Each quarter: whether the scope is now clear enough to move to a fixed price
- At renewal: rates, caps, and performance against the original estimate
A contract repository keeps the agreement, rate schedules, and change approvals together. Contracko's contract data extraction pulls parties, dates, renewal terms, notice periods, and commercial terms such as fees and billing frequency from uploaded contracts [5]. Expiration reminders track renewal dates, end dates, notice dates, and custom events such as obligations or milestones [5]. Track spend against the cap in your billing or project system, and add each review date as a custom reminder. To try this on your own contracts, start a free trial.
Sources
[1] Acquisition.gov, FAR 16.601 and FAR 16.602, plus the FAR overhaul Part 16 model text and deviation list (definitions, conditions, ceilings, and posted deviations). acquisition.gov/far/16.601, acquisition.gov/far/16.602, acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-16, acquisition.gov/far-overhaul/far-part-deviation-guide
[2] Acquisition.gov, FAR 52.232-7 Payments under Time-and-Materials and Labor-Hour Contracts and FAR 31.205-26 Material costs (payment rules and the materials exception). acquisition.gov/far/52.232-7, acquisition.gov/far/31.205-26
[3] Acquisition.gov, FAR 12.207 Contract type (limits on T&M for commercial services). acquisition.gov/far/12.207
[4] Acquisition.gov, FAR 16.103 Negotiating contract type (avoiding protracted use of T&M). acquisition.gov/far/16.103
[5] Contracko. Contract data extraction guide and expiration reminders page. contracko.com/docs/contract-data-extraction, contracko.com/features/expiration-reminder
[6] Contracko. Free business contract review tool. contracko.com/tools/contract-review